Capital Plan Updates

HEADQUARTERS RENDERING

New Southwest Branch / Headquarters

Estimated Cost = $23,025,000

PROject plan

Replace the Southwest Branch with a larger, modern Library constructed on land made available by Roy City

Project will be overseen by Prescott Muir Architects

Progress so far

  • Site survey completed
  • Geotechnical report completed
  • Schematic design signed off
  • Design process completed
  • Project out to bid
  • Project completed

Read more...

OGDEN VALLEY BRANCH

Ogden Valley Branch

Estimated Cost = $165,000

PROject plan

Add safe, street parking at the Ogden Valley Branch

Project will be overseen by Prescott Muir Architects

Progress so far

  • Site survey completed
  • Geotechnical reports completed
  • Schematic design completed
  • Project has been awarded
  • Work accomplished
  • Quality review in progress
  • Project completed

Read more...

MAIN LIBRARY

Main Library

Estimated Cost = $16,810,000

PROject plan

Renovate and upgrade the historic Main Library

Project will be overseen by EDA Architects, Inc.

Progress so far

  • Asbestos abatement investigation completed
  • Water table mitigation investigation completed
  • Service space adjacency design underway
  • Schematic design signed off
  • Design development completed
  • Construction documents underway
  • Projected awarded: July 2016
  • Materials handling systems installed: August 2017
  • Third floor construction completed: September 2017
  • Books moved to second floor: October 2017
  • Second floor construction completed: October 2017
  • Books moved to first floor: October 2017
  • Substantial completion: December 2017
  • Technology infrastructure installed: January 2018
  • Furniture installed: February 2018
  • Grand opening: April 4, 2018, 12pm
  • Re-dedication: April 7, 2018, 2pm

READ MORE...

 

North Branch

Estimated Cost = $5,000,000

PROject plan

Modernize and double the space available to users of the North Branch

Project will be overseen by EDA Architects, Inc.

Progress so far

  • Schematic design underway
  • Project awarded: May 2017
  • Demolition completed: July 2017
  • Materials handling sysgtems reinstalled: November 2017
  • Substantial completion: February 2018
  • Technology infrastructure installed: March 2018
  • Furniture installed: April 2018
  • Books and Materials moved to shelving: April 2018
  • Grand opening: Late Spring, Early Summer 2018

Read More...